Research on Borehole Construction Process of Ground Gas Drainage in Tunlan Coal Mine
Author(s): QI Chun-ming, Xishan Coal Electricity Group Company Limited
Pages: 53-
54+57
Year: 2015
Issue:
3
Journal: Coal Engineering
Keyword: large aperture; ground gas drainage borehole; cavity expansion; once-through drilling; borehole construction process;
Abstract: According to characteristics of the No. 3 ground gas drainage boreholes of Tunlan Coal Mine,the construction process of drainage borehole was designed,including drilling preparation,drilling,casing and pipe fixing. The maximum hole inclination of the Φ914mm,360 m gas piping shaft was 40’,final hole maximum deviation was 0. 89 m,the casing was smooth,pipe fixing quality was favorable,the construction safety requirements was satisfied and obvious economic benefit was achieved.