Open Tunnel Boring Machine Go Through Station of Chongqing Rail Line 6
Author(s): 
Pages: 58-63
Year: Issue:  6
Journal: Urban Mass Transit

Abstract: 介绍重庆轨道交通6号线一期工程敞开式全断面岩石掘进机(TBM)试验段的工程情况.结合敞开式TBM的机型特点和总工期要求,综合考虑TBM施工段所经过的区间及车站施工的具体情况,提出了敞开式TBM在城市轨道交通工程施工中掘进过站、步进过站以及步进通过车站中板的过站方案,保证TBM在站内能不停机、不等待、快速施工、顺利过站,成功解决了敞开式TBM在轨道交通施工中的过站难题,为敞开式TBM逐渐大规模应用于...